Global searching is not enabled.
Skip to main content
Page

Procedure to Complete a Project Network

Completion requirements
View

STEP

ACTION

1

Use the WBS and activity sequencing to complete the network

2

Decide which activities will be the start and finish activities

3

Link the activities to their predecessors as identified in the activity sequencing

4

All nodes must be entering or exit lines except for the start and finish nodes

5

Ensure that there are no loops

6

Eliminate superfluous lines

Example: Pool Installation Project

The table below demonstrates the work breakdown structure and activity sequencing for a pool Installation:

ACTIVITY NUMBER

ACTIVITY/WORK PACKAGE

DURATION

PREDECESSOR

RESOURCES

1

Decide on the pool shape

1 day

Start

Owner

2

Install pump

3 days

8

1 x electrician

3

Dig hole

10 days

1

4 x labourer

4

Order pool

1 day

1

Project Manager

5

Insert pool

4 days

3 and 4

4 x labourer

6

Test functions

1 day

2 and 7

Proj. Manager + Owner

7

Lay paving

4 days

8

2 x pavers

8

Connect water pipes

2 days

5

1 x plumbers

Note: For demonstration purposes, the activities have been kept at a high level only. Specific activity can be broken down into numerous sub-tasks.

Below is the Logic Network for the above project:  Precedence Diagram – Pool Installation Project